ALL SAINTS' BUILDING PROJECT

Stay tuned for phase two - offices for the Rector & Parish Administrator

Building Dedication

Service

Building Dedication
Bulletin

Dedication service.jpg

Week 60: June 6 - 12,  2021

Building Dedication Service

That they all may be one
That they all may be one

press to zoom
The parish gathers for the start of the service
The parish gathers for the start of the service

press to zoom
Katie leads the recession at the end of the service
Katie leads the recession at the end of the service

press to zoom
That they all may be one
That they all may be one

press to zoom
1/30

Week 59: May 30 - Jun 5

Week 58: May 23 - 29

Week 57: May 16 - 22

Punch list items basically all done

Week 56: May 9 - 15,  2021

Double checking that punch list items are complete

Shasta has a laid-back approach to supervision
Shasta has a laid-back approach to supervision

press to zoom
Shasta has a laid-back approach to supervision
Shasta has a laid-back approach to supervision

press to zoom
1/1

Week 55: May 2 - 8, 2021

More punch list items - wire secured and basement walls sealed

Crawl space under new addition
Crawl space under new addition

press to zoom
Sealant foam
Sealant foam

press to zoom
What a clean crawlspace!
What a clean crawlspace!

press to zoom
Crawl space under new addition
Crawl space under new addition

press to zoom
1/5

Week 54: Apr 25 - May 1,  2021

New microphone wires run & speakers finally get reconnected

We go from speakers on the floor, CD player, and 3 cameras
We go from speakers on the floor, CD player, and 3 cameras

press to zoom
To overhead speakers connected, organ fully connected, and 1 camera
To overhead speakers connected, organ fully connected, and 1 camera

press to zoom
We go from speakers on the floor, CD player, and 3 cameras
We go from speakers on the floor, CD player, and 3 cameras

press to zoom
1/2

Week 53: April 18 - 24, 2021

Continue working on punch list items - Ground behind church graded

Ground graded behind church
Ground graded behind church

press to zoom
Ready for landscaping
Ready for landscaping

press to zoom
Trim along the new vinyl
Trim along the new vinyl

press to zoom
Ground graded behind church
Ground graded behind church

press to zoom
1/8

Week 52: April 11 - 17,  2021

Waiting on punch list items

Easter week
Easter week

press to zoom
Easter week
Easter week

press to zoom
1/1

Week 51: April 4 - 10, 2021

Continue working on punch list items - some chair rail is replaced

Warped chair rail replaced
Warped chair rail replaced

press to zoom
Warped chair rail replaced
Warped chair rail replaced

press to zoom
1/1

Week 50: Mar 28 - Apr 3,  2021

Waiting on punch list items

Palm Sunday
Palm Sunday

press to zoom
Palm Sunday
Palm Sunday

press to zoom
1/1

Week 49: March 21 - 27, 2021

Microphone floor boxes redone

Mic boxes need support
Mic boxes need support

press to zoom
Cutting around old boxes
Cutting around old boxes

press to zoom
Ready to run microphone wires
Ready to run microphone wires

press to zoom
Mic boxes need support
Mic boxes need support

press to zoom
1/4

Week 48: March 14 - 20,  2021

Waiting on punch list items

Waiting on punch list items
Waiting on punch list items

press to zoom
Waiting on punch list items
Waiting on punch list items

press to zoom
1/1

Week 47: March 7 - 13, 2021

Work continues on punch list - all
new altar rail kneelers arrive

New altar rail kneelers below 100 yr old rail
New altar rail kneelers below 100 yr old rail

press to zoom

press to zoom
Altar rail kneelers change colors
Altar rail kneelers change colors

press to zoom
New altar rail kneelers below 100 yr old rail
New altar rail kneelers below 100 yr old rail

press to zoom
1/5

Week 46: Feb 28 - Mar 6,  2021

Work continues on punch list - pew cushions - altar rail kneelers

Feb 28
Feb 28

1st successful live-stream to Facebook & YouTube at the same time from one camera (but still using "back-up" cameras...just in case)

press to zoom
Mar 3
Mar 3

Microphone cables run to boxes

press to zoom
Mar 4
Mar 4

Pew cushions and pew kneelers all finished

press to zoom
Feb 28
Feb 28

1st successful live-stream to Facebook & YouTube at the same time from one camera (but still using "back-up" cameras...just in case)

press to zoom
1/5

Week 45: February 21 - 27, 2021

Continue working on punch list items

Feb 21
Feb 21

press to zoom
Feb 21
Feb 21

press to zoom
1/1

Week 44: February 14 - 20,  2021

Work continues on punch list

Feb 14
Feb 14

Red paraments in memory of Kay

press to zoom
Feb 14
Feb 14

Red paraments in memory of Kay

press to zoom
1/1

Week 43: February 7 - 13, 2021

Punch list items started - sound engineer consulted - organ returns!

Jan 7
Jan 7

Organ returns - back to live music - YAY!

press to zoom
Jan 7
Jan 7

Various "lights" blessed for Candlemas

press to zoom
Jan 7
Jan 7

Organ returns - back to live music - YAY!

press to zoom
1/2

Week 42: Jan 31 -  Feb 6, 2021

Electrical & microphone boxes

Feb 4
Feb 4

Electrical boxes

press to zoom
Feb 4
Feb 4

Microphone cables and electrical cables will connect inside

press to zoom
Feb 4
Feb 4

They can be closed up when not in use

press to zoom
Feb 4
Feb 4

Electrical boxes

press to zoom
1/3

Week 41: January 24 - 30, 2021

No work - waiting on electrical & microphone boxes

Jan 24
Jan 24

A beautiful Sunday for church

press to zoom
Jan 24
Jan 24

A beautiful Sunday for church

press to zoom
1/1

Week 40: January 17 - 23, 2021

100 yr old altar rail modified and reinstalled

Jan 21
Jan 21

New threshold into the narthex

press to zoom
Jan 21
Jan 21

Voilá - 100 year old rails reused - think of all the people who knelt at those rails for communion over the past 100 years

press to zoom
Jan 20
Jan 20

New railings

press to zoom
Jan 21
Jan 21

New threshold into the narthex

press to zoom
1/9

Week 39: January 10 - 16, 2021

Kneelers reconnected

Jan 10
Jan 10

Pews all back in nave and ready for kneelers

press to zoom
Jan 12
Jan 12

Kneelers get reconnected

press to zoom
Jan 12
Jan 12

Finding the correct kneelers to fit on the correct pews

press to zoom
Jan 10
Jan 10

Pews all back in nave and ready for kneelers

press to zoom
1/4

Week 38: January 3 - 9, 2021

Pendant lights installed - snow breaks - pews return - speakers rehung

Jan 7
Jan 7

Pendant lights get hung

press to zoom
Jan 7
Jan 7

"Stage" lighting aimed towards the chancel

press to zoom
Jan 8
Jan 8

Welcome...

press to zoom
Jan 7
Jan 7

Pendant lights get hung

press to zoom
1/11

Week 37: Dec 27 - Jan 2, 2021

New pendant lights arrive

Dec 29
Dec 29

Late night delivery

press to zoom
Dec 29
Dec 29

An entire pallet worth of lights

press to zoom
Dec 29
Dec 29

But success!

press to zoom
Dec 29
Dec 29

Late night delivery

press to zoom
1/4

Week 36: December 20 - 26, 2020

New door hardware - picture rails - aumbrys painted

Dec 20
Dec 20

New handles to enter sanctuary

press to zoom
Dec 20
Dec 20

Door hardware to exit sanctuary

press to zoom
Dec 20
Dec 20

North aumbry

press to zoom
Dec 20
Dec 20

New handles to enter sanctuary

press to zoom
1/5

Week 35: December 13 - 19, 2020

Ducts get cleaned out

Dec 17
Dec 17

Truck in position

press to zoom
Dec 17
Dec 17

Bags inflated

press to zoom
Dec 17
Dec 17

Special cleaning wire

press to zoom
Dec 17
Dec 17

Truck in position

press to zoom
1/4

Week 34: December 6 - 12, 2020

New altar and retables

Dec 6
Dec 6

New altar with an inscription from John, "Sir we wish to see Jesus"

press to zoom
Dec 6
Dec 6

New retable for flowers etc

press to zoom
Dec 6
Dec 6

Ready for Sunday service on Advent 2

press to zoom
Dec 6
Dec 6

New altar with an inscription from John, "Sir we wish to see Jesus"

press to zoom
1/3

Week 33: Nov 29 - Dec 5, 2020

Outside lights, stage lights, aumbry lights, floor trim, electrical outlets

Dec 1
Dec 1

Outside lights rehung

press to zoom
Dec 1
Dec 1

Lights in aumbry

press to zoom
Dec 1
Dec 1

All lights are on dimmers so there are lots of ways to adjust the brightness

press to zoom
Dec 1
Dec 1

Outside lights rehung

press to zoom
1/8

Week 32: November 22 - 28, 2020

Floor gets final coat of sealant -
new carpet in the narthex

Nov 24
Nov 24

Floor getting final coat of sealant

press to zoom
Nov 24
Nov 24

Now needs to dry

press to zoom
Nov 25
Nov 25

Floor close to being all set up and dry

press to zoom
Nov 24
Nov 24

Floor getting final coat of sealant

press to zoom
1/5

Week 31: November 15 - 21, 2020

Fiber in MH - window hardware - trim painting - picture rails

Nov 15
Nov 15

Cleaned up for Sunday services

press to zoom
Nov 15
Nov 15

Ready for services

press to zoom
Nov 20
Nov 20

Picture rail installed

press to zoom
Nov 15
Nov 15

Cleaned up for Sunday services

press to zoom
1/7

Week 30: November 8 - 14, 2020

Roofing, cove lighting, trim painting, kneelers recovered, FIBER working!

Nov 8
Nov 8

1/4 round pieces drying to go along the baseboard

press to zoom
Nov 8
Nov 8

Continuing the trim painting

press to zoom
Nov 13
Nov 13

New vinyl covering on the kneelers

press to zoom
Nov 8
Nov 8

1/4 round pieces drying to go along the baseboard

press to zoom
1/14

Week 29: November 1 - 7, 2020

Floor stained, new handrails, fiber optics arrives, floor covered

Nov 3
Nov 3

Last section of fiber to be connected. Conduit had to be bored under our neighbor's driveway and then this last section connected.

press to zoom
Nov 3
Nov 3

Not bad looking for a 100 year old fir tongue and groove floor. But it won't ever be able to be sanded and refinished again, not enough groove left for the tongue. ; )

press to zoom
Nov 5
Nov 5

New ADA compliant hand rails for the new center ramp

press to zoom
Nov 3
Nov 3

Last section of fiber to be connected. Conduit had to be bored under our neighbor's driveway and then this last section connected.

press to zoom
1/8

Week 28: October 25 - 31, 2020

More painting, new floor installed and old floor refinished

Oct 26
Oct 26

Tongue & groove fir floor board for the addition

press to zoom
Oct 26
Oct 26

Collar ties and coves painted

press to zoom
Oct 31
Oct 31

Floor all vacuumed and ready for stain and then sealant

press to zoom
Oct 26
Oct 26

Tongue & groove fir floor board for the addition

press to zoom
1/12

Week 27: October 18 - 24, 2020

Trim work and priming completed and painting started

Oct 19
Oct 19

Fiber run under hwy 40

press to zoom
Oct 19
Oct 19

Fiber gets run under our berm to the church

press to zoom
Oct 25
Oct 25

The collar ties are the first things painted back to the final brown

press to zoom
Oct 19
Oct 19

Fiber run under hwy 40

press to zoom
1/14

Week 26: October 11 - 17, 2020

Fiber optics, beginning of trim work and coves

Oct 13
Oct 13

Blowing compressed air to see if we have clear conduit all the way to the church to run the fiber optics cables

press to zoom
Oct 13
Oct 13

Bummer, there is a missing section. So a boring machine will need to lay conduit for our fiber optics under our neighbors driveway to connect into the conduit we already have running under our berm along the parking lot all the way to the church.

press to zoom
Oct 17
Oct 17

All cleaned up so services can be held inside on Sunday.

press to zoom
Oct 13
Oct 13

Blowing compressed air to see if we have clear conduit all the way to the church to run the fiber optics cables

press to zoom
1/17

Week 25: October 4 - 10, 2020

Sheetrock completed, bead board for ceiling arrives, priming starts

Oct 6
Oct 6

Sheetrock all finished

press to zoom
Oct 7
Oct 7

Ceiling bead board arrives

press to zoom
Oct 9
Oct 9

Bead board ready to get installed

press to zoom
Oct 6
Oct 6

Sheetrock all finished

press to zoom
1/6

Week 24: Sep 27 - Oct 3, 2020

Sheetrocking

Sep 29
Sep 29

Sheetrock arrives

press to zoom
Sep 29
Sep 29

Lots of sheetrock to be hung

press to zoom
Oct 2
Oct 2

New west wall done

press to zoom
Sep 29
Sep 29

Sheetrock arrives

press to zoom
1/10

Week 23: September 20 - 26, 2020

Exterior painting, insulating

Sep 21
Sep 21

Overhangs to protect HVAC units

press to zoom
Sep 22
Sep 22

North wall starts to get painted

press to zoom
Sep 25
Sep 25

Insulation done

press to zoom
Sep 21
Sep 21

Overhangs to protect HVAC units

press to zoom
1/13

Week 22: September 13 - 19, 2020

Start of new wiring and other electrical work, new collar tie

September 15
September 15

Old chancel track lighting and speakers ready to come down

press to zoom
September 15
September 15

Out with the old

press to zoom
September 17
September 17

New collar tie

press to zoom
September 15
September 15

Old chancel track lighting and speakers ready to come down

press to zoom
1/6

Week 21: September 6 - 12, 2020

Getting ready to start

interior finish work

September 12
September 12

Getting ready to start working on the interior

press to zoom
September 12
September 12

Old lighting removed

press to zoom
September 12
September 12

Getting ready to start working on the interior

press to zoom
1/2

Week 20: August 30 - Sep 5, 2020

Board & batten and all siding complete, ready for outside painting

August 31
August 31

North side done & all windows framed

press to zoom
August 31
August 31

Boards done on west side & windows partly framed

press to zoom
September 3
September 3

Ready for the inside work to begin

press to zoom
August 31
August 31

North side done & all windows framed

press to zoom
1/17

Week 19: August 23 - 29, 2020

Pews removed, insulation, siding, board and batten, new HVAC

August 24
August 24

Pews being stored in Christian Ed until they can be repaired/refinished

press to zoom
August 24
August 24

Final two big windows installed

press to zoom
August 28
August 28

Crawl space under the new addition

press to zoom
August 24
August 24

Pews being stored in Christian Ed until they can be repaired/refinished

press to zoom
1/14

Week 18: August 16 - 22, 2020

Front door changed, battens removed, insulation, pews detached

August 17
August 17

The Episcopal Church welcomes you...now with proper swinging doors

press to zoom
August 17
August 17

Front door now centered on the wall

press to zoom
August 21
August 21

Entire building will now have insulation

press to zoom
August 17
August 17

The Episcopal Church welcomes you...now with proper swinging doors

press to zoom
1/11

Week 17: August 9 - 15, 2020

Narthex cleared out & doors removed, old windows replaced

August 11
August 11

Narthex cleared out

press to zoom
August 11
August 11

More stuff to cram into Memorial Hall

press to zoom
August 13
August 13

Small stained glass windows removed to make room for new windows where the chancel used to be

press to zoom
August 11
August 11

Narthex cleared out

press to zoom
1/15

Week 16: August 2 - 8, 2020

Last Eucharist, new windows, bye bye back wall, chancel platform started

August 2
August 2

Last Eucharist in the old chancel

press to zoom
August 2
August 2

press to zoom
August 7
August 7

Start of a new platform and new windows to replace the old

press to zoom
August 2
August 2

Last Eucharist in the old chancel

press to zoom
1/27

Week 15: July 26 - August 1, 2020

Plywood, rafters, roof decking,

removing old lathe and plaster

July 28
July 28

North wall

press to zoom
July 28
July 28

Back wall windows cut out

press to zoom
July 31
July 31

More of the backside of the original lath and plaster back wall where the light switches for the chancel were

press to zoom
July 28
July 28

North wall

press to zoom
1/13

Week 14: July 19 - 25, 2020

WE GO VERTICAL !!!

July 22
July 22

Back wall

press to zoom
July 22
July 22

North wall

press to zoom
July 24
July 24

Back (west) wall

press to zoom
July 22
July 22

Back wall

press to zoom
1/21

Week 13: July 12 - 18, 2020

Floor joists down &
prepping for moment frame

July 15
July 15

Hole cut out in the old foundation wall to connect the old and new crawl spaces

press to zoom
July 15
July 15

Laying out the floor joists

press to zoom
July 16
July 16

Old siding removed for steel moment frame

press to zoom
July 15
July 15

Hole cut out in the old foundation wall to connect the old and new crawl spaces

press to zoom
1/5

Week 12: July 5 - 11, 2020

Concrete core testing

July 9
July 9

Core sample from the south wall

press to zoom
July 9
July 9

Core sample from the footing

press to zoom
July 9
July 9

Sample from the west wall

press to zoom
July 9
July 9

Core sample from the south wall

press to zoom
1/4

Week 11: June 28 - July 4, 2020

Supplies arrive &

concrete tested

July 1
July 1

Supplies arrive

press to zoom
July 1
July 1

Floor joists and plywood

press to zoom
July 2
July 2

Testing the strength of the concrete

press to zoom
July 1
July 1

Supplies arrive

press to zoom
1/4

Week 10: June 21 - 27, 2020

Week 9: June 14 - 20, 2020

No work done - rained out as well as waiting on concrete

Week 8: June 7 - 13, 2020

Gravel for the basement

June 12
June 12

Gravel to fill in the basement

press to zoom
June 12
June 12

press to zoom
June 12
June 12

Gravel to fill in the basement

press to zoom
1/2

Week 7: May 31 - June 6, 2020

Basement wall insulation

and backfilling

May 31
May 31

Insulation around the basement walls

press to zoom
May 31
May 31

And a little bit of rain

press to zoom
June 2
June 2

Ready to start putting in the floor joists

press to zoom
May 31
May 31

Insulation around the basement walls

press to zoom
1/4

Week 6: May 24 - 30, 2020

Basement walls poured

May 24
May 24

Basement walls framed

press to zoom
May 24
May 24

Steel tied

press to zoom
May 27
May 27

press to zoom
May 24
May 24

Basement walls framed

press to zoom
1/16

Week 5: May 17 - 23, 2020

New front ramp

May 21
May 21

New front ramp

press to zoom
May 21
May 21

No more tripping on step...yay!