ALL SAINTS' BUILDING PROJECT
Week 34: December 6 - 12, 2020
New altar and retables
Week 33: Nov 29 - Dec 5, 2020
Outside lights, stage lights, aumbry lights, floor trim, electrical outlets
Week 32: November 22 - 28, 2020
Floor gets final coat of sealant -
new carpet in the narthex
Week 31: November 15 - 21, 2020
Fiber in MH - window hardware - trim painting - picture rails
Week 30: November 8 - 14, 2020
Roofing, cove lighting, trim painting, kneelers recovered, FIBER working!
Week 29: November 1 - 7, 2020
Floor stained, new handrails, fiber optics arrives, floor covered
Week 28: October 25 - 31, 2020
More painting, new floor installed and old floor refinished
Week 27: October 18 - 24, 2020
Trim work and priming completed and painting started
Week 26: October 11 - 17, 2020
Fiber optics, beginning of trim work and coves
Week 25: October 4 - 10, 2020
Sheetrock completed, bead board for ceiling arrives, priming starts
Week 24: Sep 27 - Oct 3, 2020
Sheetrocking
Week 23: September 20 - 26, 2020
Exterior painting, insulating
Week 22: September 13 - 19, 2020
Start of new wiring and other electrical work, new collar tie
Week 21: September 6 - 12, 2020
Getting ready to start
interior finish work
Week 20: August 30 - Sep 5, 2020
Board & batten and all siding complete, ready for outside painting
Week 19: August 23 - 29, 2020
Pews removed, insulation, siding, board and batten, new HVAC
Week 18: August 16 - 22, 2020
Front door changed, battens removed, insulation, pews detached
Week 17: August 9 - 15, 2020
Narthex cleared out & doors removed, old windows replaced
Week 16: August 2 - 8, 2020
Last Eucharist, new windows, bye bye back wall, chancel platform started
Week 15: July 26 - August 1, 2020
Plywood, rafters, roof decking,
removing old lathe and plaster
Week 14: July 19 - 25, 2020
WE GO VERTICAL !!!
Week 13: July 12 - 18, 2020
Floor joists down &
prepping for moment frame
Week 12: July 5 - 11, 2020
Concrete core testing
Week 11: June 28 - July 4, 2020
Supplies arrive &
concrete tested
Week 10: June 21 - 27, 2020
Week 9: June 14 - 20, 2020
No work done - rained out as well as waiting on concrete
Week 8: June 7 - 13, 2020
Gravel for the basement
Week 7: May 31 - June 6, 2020
Basement wall insulation
and backfilling
Week 6: May 24 - 30, 2020
Basement walls poured
Week 5: May 17 - 23, 2020
New front ramp
Week 4: May 10 - 16, 2020
Footing poured
Week 3: May 3 - 9, 2020
Fill and compaction
Week 2: April 26 - May 2, 2020
Rained out, so check out the "toys"
Week 1: April 19 - 25, 2020
Septic work, Groundbreaking, front step removed, foundation dug