ALL SAINTS' BUILDING PROJECT

Week 33: Nov 29 - Dec 5, 2020

Outside lights, stage lights, aumbry lights, floor trim, electrical outlets

Week 32: November 22 - 28, 2020

Floor gets final coat of sealant -
new carpet in the narthex

Week 31: November 15 - 21, 2020

Fiber in MH - window hardware - trim painting - picture rails

Week 30: November 8 - 14, 2020

Roofing, cove lighting, trim painting, kneelers recovered, FIBER working!

Week 25: October 4 - 10, 2020

Sheetrock completed, bead board for ceiling arrives, priming starts

Week 23: September 20 - 26, 2020

Exterior painting, insulating

Week 22: September 13 - 19, 2020

Start of new wiring and other electrical work, new collar tie

Week 21: September 6 - 12, 2020

Getting ready to start

interior finish work

Week 20: August 30 - Sep 5, 2020

Board & batten and all siding complete, ready for outside painting

Week 16: August 2 - 8, 2020

Last Eucharist, new windows, bye bye back wall, chancel platform started

Week 14: July 19 - 25, 2020

WE GO VERTICAL !!!

Week 11: June 28 - July 4, 2020

Supplies arrive &

concrete tested

Week 10: June 21 - 27, 2020

Week 9: June 14 - 20, 2020

No work done - rained out as well as waiting on concrete

Week 8: June 7 - 13, 2020

Gravel for the basement

Week 6: May 24 - 30, 2020

Basement walls poured

Week 2: April 26 - May 2, 2020

Rained out, so check out the "toys"

All Saints' Groundbreaking Service.jpg

ALL SAINTS' EPISCOPAL CHURCH

Follow

Contact

Mailing Address:

Physical Address:

  • Facebook Social Icon
  • YouTube Social  Icon

PO Box 1923
Whitefish, MT 59937

2048 Conn Rd.
Columbia Falls, Montana

©2021 by All Saints' Episcopal Church

Oct 13

Bummer, there is a missing section. So a boring machine will need to lay conduit for our fiber optics under our neighbors driveway to connect into the conduit we already have running under our berm along the parking lot all the way to the church.