ALL SAINTS' BUILDING PROJECT
Stay tuned for phase two - offices for the Rector & Parish Administrator
Building Dedication
Service
Building Dedication
Bulletin
Week 60: June 6 - 12, 2021
Building Dedication Service
Week 59: May 30 - Jun 5
Week 58: May 23 - 29
Week 57: May 16 - 22
Punch list items basically all done
Week 56: May 9 - 15, 2021
Double checking that punch list items are complete
Week 55: May 2 - 8, 2021
More punch list items - wire secured and basement walls sealed
Week 54: Apr 25 - May 1, 2021
New microphone wires run & speakers finally get reconnected
Week 53: April 18 - 24, 2021
Continue working on punch list items - Ground behind church graded
Week 52: April 11 - 17, 2021
Waiting on punch list items
Week 51: April 4 - 10, 2021
Continue working on punch list items - some chair rail is replaced
Week 50: Mar 28 - Apr 3, 2021
Waiting on punch list items
Week 49: March 21 - 27, 2021
Microphone floor boxes redone
Week 48: March 14 - 20, 2021
Waiting on punch list items
Week 47: March 7 - 13, 2021
Work continues on punch list - all
new altar rail kneelers arrive
Week 46: Feb 28 - Mar 6, 2021
Work continues on punch list - pew cushions - altar rail kneelers
1st successful live-stream to Facebook & YouTube at the same time from one camera (but still using "back-up" cameras...just in case)
Microphone cables run to boxes
Pew cushions and pew kneelers all finished
1st successful live-stream to Facebook & YouTube at the same time from one camera (but still using "back-up" cameras...just in case)
Week 45: February 21 - 27, 2021
Continue working on punch list items
Week 44: February 14 - 20, 2021
Work continues on punch list
Red paraments in memory of Kay
Red paraments in memory of Kay
Week 43: February 7 - 13, 2021
Punch list items started - sound engineer consulted - organ returns!
Organ returns - back to live music - YAY!
Various "lights" blessed for Candlemas
Organ returns - back to live music - YAY!
Week 42: Jan 31 - Feb 6, 2021
Electrical & microphone boxes
Electrical boxes
Microphone cables and electrical cables will connect inside
They can be closed up when not in use
Electrical boxes
Week 41: January 24 - 30, 2021
No work - waiting on electrical & microphone boxes
A beautiful Sunday for church
A beautiful Sunday for church
Week 40: January 17 - 23, 2021
100 yr old altar rail modified and reinstalled
New threshold into the narthex
Voilá - 100 year old rails reused - think of all the people who knelt at those rails for communion over the past 100 years
New railings
New threshold into the narthex
Week 39: January 10 - 16, 2021
Kneelers reconnected
Pews all back in nave and ready for kneelers
Kneelers get reconnected
Finding the correct kneelers to fit on the correct pews
Pews all back in nave and ready for kneelers
Week 38: January 3 - 9, 2021
Pendant lights installed - snow breaks - pews return - speakers rehung
Pendant lights get hung
"Stage" lighting aimed towards the chancel
Welcome...
Pendant lights get hung
Week 37: Dec 27 - Jan 2, 2021
New pendant lights arrive
Late night delivery
An entire pallet worth of lights
But success!
Late night delivery
Week 36: December 20 - 26, 2020
New door hardware - picture rails - aumbrys painted
New handles to enter sanctuary
Door hardware to exit sanctuary
North aumbry
New handles to enter sanctuary
Week 35: December 13 - 19, 2020
Ducts get cleaned out
Truck in position
Bags inflated
Special cleaning wire
Truck in position
Week 34: December 6 - 12, 2020
New altar and retables
New altar with an inscription from John, "Sir we wish to see Jesus"
New retable for flowers etc
Ready for Sunday service on Advent 2
New altar with an inscription from John, "Sir we wish to see Jesus"
Week 33: Nov 29 - Dec 5, 2020
Outside lights, stage lights, aumbry lights, floor trim, electrical outlets
Outside lights rehung
Lights in aumbry
All lights are on dimmers so there are lots of ways to adjust the brightness
Outside lights rehung
Week 32: November 22 - 28, 2020
Floor gets final coat of sealant -
new carpet in the narthex
Floor getting final coat of sealant
Now needs to dry
Floor close to being all set up and dry
Floor getting final coat of sealant
Week 31: November 15 - 21, 2020
Fiber in MH - window hardware - trim painting - picture rails
Cleaned up for Sunday services
Ready for services
Picture rail installed
Cleaned up for Sunday services
Week 30: November 8 - 14, 2020
Roofing, cove lighting, trim painting, kneelers recovered, FIBER working!
1/4 round pieces drying to go along the baseboard
Continuing the trim painting
New vinyl covering on the kneelers
1/4 round pieces drying to go along the baseboard
Week 29: November 1 - 7, 2020
Floor stained, new handrails, fiber optics arrives, floor covered
Last section of fiber to be connected. Conduit had to be bored under our neighbor's driveway and then this last section connected.
Not bad looking for a 100 year old fir tongue and groove floor. But it won't ever be able to be sanded and refinished again, not enough groove left for the tongue. ; )
New ADA compliant hand rails for the new center ramp
Last section of fiber to be connected. Conduit had to be bored under our neighbor's driveway and then this last section connected.
Week 28: October 25 - 31, 2020
More painting, new floor installed and old floor refinished
Tongue & groove fir floor board for the addition
Collar ties and coves painted
Floor all vacuumed and ready for stain and then sealant
Tongue & groove fir floor board for the addition
Week 27: October 18 - 24, 2020
Trim work and priming completed and painting started
Fiber run under hwy 40
Fiber gets run under our berm to the church
The collar ties are the first things painted back to the final brown
Fiber run under hwy 40
Week 26: October 11 - 17, 2020
Fiber optics, beginning of trim work and coves
Blowing compressed air to see if we have clear conduit all the way to the church to run the fiber optics cables
Bummer, there is a missing section. So a boring machine will need to lay conduit for our fiber optics under our neighbors driveway to connect into the conduit we already have running under our berm along the parking lot all the way to the church.
All cleaned up so services can be held inside on Sunday.
Blowing compressed air to see if we have clear conduit all the way to the church to run the fiber optics cables
Week 25: October 4 - 10, 2020
Sheetrock completed, bead board for ceiling arrives, priming starts
Sheetrock all finished
Ceiling bead board arrives
Bead board ready to get installed
Sheetrock all finished
Week 24: Sep 27 - Oct 3, 2020
Sheetrocking
Sheetrock arrives
Lots of sheetrock to be hung
New west wall done
Sheetrock arrives
Week 23: September 20 - 26, 2020
Exterior painting, insulating
Overhangs to protect HVAC units
North wall starts to get painted
Insulation done
Overhangs to protect HVAC units
Week 22: September 13 - 19, 2020
Start of new wiring and other electrical work, new collar tie
Old chancel track lighting and speakers ready to come down
Out with the old
New collar tie
Old chancel track lighting and speakers ready to come down
Week 21: September 6 - 12, 2020
Getting ready to start
interior finish work
Getting ready to start working on the interior
Old lighting removed
Getting ready to start working on the interior
Week 20: August 30 - Sep 5, 2020
Board & batten and all siding complete, ready for outside painting
North side done & all windows framed
Boards done on west side & windows partly framed
Ready for the inside work to begin
North side done & all windows framed
Week 19: August 23 - 29, 2020
Pews removed, insulation, siding, board and batten, new HVAC
Pews being stored in Christian Ed until they can be repaired/refinished
Final two big windows installed
Crawl space under the new addition
Pews being stored in Christian Ed until they can be repaired/refinished
Week 18: August 16 - 22, 2020
Front door changed, battens removed, insulation, pews detached
The Episcopal Church welcomes you...now with proper swinging doors
Front door now centered on the wall
Entire building will now have insulation
The Episcopal Church welcomes you...now with proper swinging doors
Week 17: August 9 - 15, 2020
Narthex cleared out & doors removed, old windows replaced
Narthex cleared out
More stuff to cram into Memorial Hall
Small stained glass windows removed to make room for new windows where the chancel used to be
Narthex cleared out
Week 16: August 2 - 8, 2020
Last Eucharist, new windows, bye bye back wall, chancel platform started
Last Eucharist in the old chancel
Start of a new platform and new windows to replace the old
Last Eucharist in the old chancel
Week 15: July 26 - August 1, 2020
Plywood, rafters, roof decking,
removing old lathe and plaster
North wall
Back wall windows cut out
More of the backside of the original lath and plaster back wall where the light switches for the chancel were
North wall
Week 14: July 19 - 25, 2020
WE GO VERTICAL !!!
Back wall
North wall
Back (west) wall
Back wall
Week 13: July 12 - 18, 2020
Floor joists down &
prepping for moment frame
Hole cut out in the old foundation wall to connect the old and new crawl spaces
Laying out the floor joists
Old siding removed for steel moment frame
Hole cut out in the old foundation wall to connect the old and new crawl spaces
Week 12: July 5 - 11, 2020
Concrete core testing
Core sample from the south wall
Core sample from the footing
Sample from the west wall
Core sample from the south wall
Week 11: June 28 - July 4, 2020
Supplies arrive &
concrete tested
Supplies arrive
Floor joists and plywood
Testing the strength of the concrete
Supplies arrive
Week 10: June 21 - 27, 2020
Week 9: June 14 - 20, 2020
No work done - rained out as well as waiting on concrete
Week 8: June 7 - 13, 2020
Gravel for the basement
Gravel to fill in the basement
Gravel to fill in the basement
Week 7: May 31 - June 6, 2020
Basement wall insulation
and backfilling
Insulation around the basement walls
And a little bit of rain
Ready to start putting in the floor joists
Insulation around the basement walls
Week 6: May 24 - 30, 2020
Basement walls poured
Basement walls framed
Steel tied
Basement walls framed
Week 5: May 17 - 23, 2020
New front ramp
New front ramp
No more tripping on step...yay!
Panels for framing the basement walls
New front ramp
Week 4: May 10 - 16, 2020
Footing poured
Getting ready to pour
Up and over we go
Pouring all the way around the footings
Getting ready to pour
Week 3: May 3 - 9, 2020
Fill and compaction
Adding fill material for compaction
Getting ready for more compaction
Hauling away extra material
Adding fill material for compaction
Week 2: April 26 - May 2, 2020
Rained out, so check out the "toys"
Rained out
Have to wait to do compaction
Check out the "toys"
Rained out
Week 1: April 19 - 25, 2020
Septic work, Groundbreaking, front step removed, foundation dug
Front step will be removed and front door centered
Sanctuary will be extended to the west
Sun comes out following an afternoon thunderstorm
Front step will be removed and front door centered