top of page

ALL SAINTS' BUILDING PROJECT

Stay tuned for phase two - offices for the Rector & Parish Administrator

Building Dedication

Service

Building Dedication
Bulletin

Dedication service.jpg

Week 60: June 6 - 12,  2021

Building Dedication Service

Week 59: May 30 - Jun 5

Week 58: May 23 - 29

Week 57: May 16 - 22

Punch list items basically all done

Week 56: May 9 - 15,  2021

Double checking that punch list items are complete

Week 55: May 2 - 8, 2021

More punch list items - wire secured and basement walls sealed

Week 54: Apr 25 - May 1,  2021

New microphone wires run & speakers finally get reconnected

Week 53: April 18 - 24, 2021

Continue working on punch list items - Ground behind church graded

Week 52: April 11 - 17,  2021

Waiting on punch list items

Week 51: April 4 - 10, 2021

Continue working on punch list items - some chair rail is replaced

Week 50: Mar 28 - Apr 3,  2021

Waiting on punch list items

Week 49: March 21 - 27, 2021

Microphone floor boxes redone

Week 48: March 14 - 20,  2021

Waiting on punch list items

Week 47: March 7 - 13, 2021

Work continues on punch list - all
new altar rail kneelers arrive

Week 46: Feb 28 - Mar 6,  2021

Work continues on punch list - pew cushions - altar rail kneelers

Week 45: February 21 - 27, 2021

Continue working on punch list items

Week 44: February 14 - 20,  2021

Work continues on punch list

Week 43: February 7 - 13, 2021

Punch list items started - sound engineer consulted - organ returns!

Week 42: Jan 31 -  Feb 6, 2021

Electrical & microphone boxes

Week 41: January 24 - 30, 2021

No work - waiting on electrical & microphone boxes

Week 40: January 17 - 23, 2021

100 yr old altar rail modified and reinstalled

Week 39: January 10 - 16, 2021

Kneelers reconnected

Week 38: January 3 - 9, 2021

Pendant lights installed - snow breaks - pews return - speakers rehung

Week 37: Dec 27 - Jan 2, 2021

New pendant lights arrive

Week 36: December 20 - 26, 2020

New door hardware - picture rails - aumbrys painted

Week 35: December 13 - 19, 2020

Ducts get cleaned out

Week 34: December 6 - 12, 2020

New altar and retables

Week 33: Nov 29 - Dec 5, 2020

Outside lights, stage lights, aumbry lights, floor trim, electrical outlets

Week 32: November 22 - 28, 2020

Floor gets final coat of sealant -
new carpet in the narthex

Week 31: November 15 - 21, 2020

Fiber in MH - window hardware - trim painting - picture rails

Week 30: November 8 - 14, 2020

Roofing, cove lighting, trim painting, kneelers recovered, FIBER working!

Week 29: November 1 - 7, 2020

Floor stained, new handrails, fiber optics arrives, floor covered

Week 28: October 25 - 31, 2020

More painting, new floor installed and old floor refinished

Week 27: October 18 - 24, 2020

Trim work and priming completed and painting started

Week 26: October 11 - 17, 2020

Fiber optics, beginning of trim work and coves

Week 25: October 4 - 10, 2020

Sheetrock completed, bead board for ceiling arrives, priming starts

Week 24: Sep 27 - Oct 3, 2020

Sheetrocking

Week 23: September 20 - 26, 2020

Exterior painting, insulating

Week 22: September 13 - 19, 2020

Start of new wiring and other electrical work, new collar tie

Week 21: September 6 - 12, 2020

Getting ready to start

interior finish work

Week 20: August 30 - Sep 5, 2020

Board & batten and all siding complete, ready for outside painting

Week 19: August 23 - 29, 2020

Pews removed, insulation, siding, board and batten, new HVAC

Week 18: August 16 - 22, 2020

Front door changed, battens removed, insulation, pews detached

Week 17: August 9 - 15, 2020

Narthex cleared out & doors removed, old windows replaced

Week 16: August 2 - 8, 2020

Last Eucharist, new windows, bye bye back wall, chancel platform started

Week 15: July 26 - August 1, 2020

Plywood, rafters, roof decking,

removing old lathe and plaster

Week 14: July 19 - 25, 2020

WE GO VERTICAL !!!

Week 13: July 12 - 18, 2020

Floor joists down &
prepping for moment frame

Week 12: July 5 - 11, 2020

Concrete core testing

Week 11: June 28 - July 4, 2020

Supplies arrive &

concrete tested

Week 10: June 21 - 27, 2020

Week 9: June 14 - 20, 2020

No work done - rained out as well as waiting on concrete

Week 8: June 7 - 13, 2020

Gravel for the basement

Week 7: May 31 - June 6, 2020

Basement wall insulation

and backfilling

Week 6: May 24 - 30, 2020

Basement walls poured

Week 5: May 17 - 23, 2020

New front ramp

Week 4: May 10 - 16, 2020

Footing poured

Week 3: May 3 - 9, 2020

Fill and compaction

Week 2: April 26 - May 2, 2020

Rained out, so check out the "toys"

Week 1: April 19 - 25, 2020

Septic work, Groundbreaking, front step removed, foundation dug

All Saints' Groundbreaking Service.jpg
bottom of page